How FU1 - Renting a co-location space/rack with 1 kW of power - works

Introduction

DCFootprint estimates the environmental impacts of the life cycle of the Datacenter, depending on its generic description (based on the input parameters), before computing the share of impact of each other Functional Unit.

This Functional Unit “1” is defined in the Ademe Cloud & Datacenter PCR, as “Provide hosting services for operation of the IT equipment”.

Version 1 - early stage version

This is the very first version of the methodology. It will evolve in the future, in order to be able to compare results between each model version. Please see the roadmap page.

To discuss about this methodology and how it should evolve, please look for an existing thread or open a new one, on community.dcfootprint.org.

Life Cycle coverage and respect of norms

Environmental display - Life Cycle stageITU L.1410 - Life Cycle stageCoverage in Ademe Cloud & DC PCRCoverage in DCFootprint’s Functional Unit
🏗️ ManufacturingRaw materials extractionMandatory✅ see the methodology section for details
🏗️ ManufacturingRaw materials processingMandatory✅ see the methodology section for details
🏗️ ManufacturingIT equipment production - Component productionExcluded from this functional unit (see FU2, FU3 and FU4)⚠️ Included as a share of the global IT impacts estimated for the Datacenter
🏗️ ManufacturingIT equipment production - Assembly⚠️ Included as a share of the global IT impacts estimated for the Datacenter from this functional unit (see FU2, FU3 and FU4)Excluded
🏗️ ManufacturingIT equipment production - Support activities of IT equipment manufacturersExcluded from this functional unit (see FU2, FU3 and FU4)Excluded
🏗️ ManufacturingSupport goods manufacturingMandatory✅ see the methodology section for details
🏗️ ManufacturingConstruction of ICT specific siteMandatory✅ see the methodology section for details
🚚 DistributionMandatoryPartially included
🔧 InstallationOptionalPartially included
⚡ UseIT equipment useExcluded from this functional unit (see FU2, FU3 and FU4)⚠️ Included as a share of the global IT impacts estimated for the Datacenter
⚡ UseSupport goods useMandatory✅ see the methodology section for details
⚡ UseOperator support activitiesMandatory✅ see the methodology section for details
⚡ UseService provider support activitesExcludedExcluded
🗑️ End of lifePreparation of ICT equipment for reuseMandatoryPartially included
🗑️ End of lifeStorage / Disassembly / Dismantling / ShredingMandatoryPartially included

Methodology

FU1Impacts(1 kW, 1 Year) = DatacenterImpacts / CommercializedPower / DatacenterLifetime

With:

DatacenterImpacts: the impacts calculated before in the Datacenter section, see the FU0 methodology.

DatacenterLifetime: the lifetime set as an input.

CommercializedPower: the total power that the provider car sell to its clients, in kW. Formula is:

CommercializedPower = TotalPowerInstalled / PowerUsageEffectiveness

Version 2

Planned for 2026.